The scheme at Longbridge Hayes involves installing a new gravity drainage system to divert surface water from the road near the double bend, an area prone to flooding, to an existing drain to the south. The project was designed in partnership with Network Rail and Severn Trent Water.
Work began earlier this month and is advancing, with crews having installed several new chambers and part of the drainage system along the route. The new system will take water from the road to an outflow approximately 220 metres away. Temporary lane and road closures remain in place, but access to businesses is being maintained throughout the works.
“"It’s good to see work progressing well on this important scheme, which will provide a long-term solution to a flooding problem that has affected Chemical Lane for many years. Teams are three weeks into the project with several new chambers installed and the deepest drain section now also installed."
The project is expected to take around three months to complete. Crews will continue to work as safely and efficiently as possible.