The comprehensive scheme, aimed at making roads safer, encouraging active travel, and improving public transport reliability, has now concluded. It features a new segregated cycle lane connecting to existing routes, dedicated bus lanes to ensure punctual public transport, and enhanced pedestrian zones.
These transportation upgrades are also designed to facilitate housing development along the vital corridor that connects Birmingham and Sandwell. Cllr Rob Grant, cabinet member for transport, highlighted the transformation from a congested route dominated by slow-moving private vehicles to one that prioritises walking, cycling, and smoother bus journeys. He stated, "This is how things should look as we work towards our longer-term ambitions of sustainable public transport, safe communities and a significant reduction in carbon emissions as people move about the city."
Cllr Roger Harmer, leader of Birmingham City Council, praised the multi-partner collaboration and thanked residents for their patience. He emphasised that success will be measured by punctual buses, safe school crossings, smooth commutes, and increased walking and cycling.
Kevin Reynolds, Head of Estates at Sandwell and West Birmingham NHS Trust, noted the scheme's importance for the thousands of patients, visitors, and staff travelling to Midland Metropolitan University Hospital. He commented, "This investment will support patients, visitors and colleagues for many years to come, while contributing to the continued regeneration of the area surrounding Midland Met."
The project was executed by civil engineering contractor McPhillips. Andrew Dunham, director at McPhillips, expressed pride in creating a safer and improved route for all users, acknowledging the careful planning required to maintain traffic flow and hospital access.
The scheme was delivered in phases: Phase 1 (Western Road junction) completed in May 2022; Phase 2 (Spring Hill, Barford Estate and Heath Street / Winson Green Road sections) in August 2024; Phase 3 (Lee Bridge and Icknield Port Road junction) in April 2026; and Phase 4 (Birmingham Treatment Centre Cycle Track) concluded in October 2026.